E-Rate Home |
Keeping on Track
 |
Notices and Tasks for the Next Funding Year: FY2027 (7/1/27 - 6/30/28) |
|
|
- FY2027Make a plan and choose products and services for which you will seek E-Rate funding for the next
funding year
- FY2027File a Form 470 in EPC to identify desired products and services
- FY2027Next steps after filing the Form 470
- FY2027Form 470 Wrap-Up Step 1: Selecting Vendors
| |
| Constraints: |
before selecting a vendor, you must wait at least 28 days after the date the Form 470 is filed and the date the RFP is issued, whichever is later |
|
- FY2027Form 470 Wrap-Up Step 2: Signing Contracts
| |
| Constraints: |
before signing a contract, you must wait at least 28 days after the date the Form 470 is filed and the date the RFP is issued, whichever is later |
|
|